| |
During the winter of 2000, a pipe contractor was attempting
to bore nearly 200 linear feet under a major five-lane highway
that serves as an artery carrying commuters to and from the
eastern suburbs of Atlanta. At first, the boring auger made
effortless progress through the wet, sandy, clay like substrate
that was full of partially decomposed biodegradable materials.
The contractor’s hopes of completing the boring ahead
of schedule were dashed when the auger struck a large vein
of Georgia Blue Granite.
Explosives were used to break the rock into small pieces that
could be removed by hand. Due to the small diameter of the
bore and the density of the granite, progress under the highway
was slow. After completing about half of the total distance,
the contractor noticed that the asphalt above the tunneling
operation was sinking, creating a dangerous dip that affected
the two westbound lanes of the highway.
After the DOT’s initial inspection, Barton Southern
Company was brought in to determine what had caused the dip
in the asphalt and propose a solution. After drilling several
inspection holes through the 12-inch thick asphalt highway
it was found that the substrate had settled about 8 inches
directly over the centerline of the tunneling operation. The
settlement was caused by existing voids created by decaying
biodegradable materials in the soft, sandy substrate that
had collapsed during the blasting.
To stabilize the soil, three rows of 1inch holes were drilled
through the roadway 3 feet on center over the tunnel. _ inch
black iron pipes were then driven through these holes to a
depth of about 10 feet (just above the top of the tunnel casing).
A water activated polyurethane grout was injected through
the pipes and easily penetrated into the void areas and wet
sandy soil. The moisture in the soil activated the grout causing
it to expand to a rigid foam that filled the voids and consolidated
the loose soil to a hardness similar to that of sandstone.
As each of the one inch holes were grouted the gap between
the substrate and the asphalt began to decrease. This indicated
that the voids were being filled and the soil was being consolidated
into a solid mass.
The stabilization was completed in five days without shutting
down the highway.
|
|
|